In a development that promises to reshape the economic landscape of southern Namibia, Koryx Copper S.A. has announced a significant escalation in the scale and efficiency of its wholly-owned Haib Copper Project. In an interim update released last week, the company confirmed that its Pre-Feasibility Study (PFS) is nearing completion, revealing a substantially upgraded operational blueprint that will see the mine process 48 million tons per annum (Mtpa) of run-of-mine material. This increased throughput, alongside a strategic pivot in processing methodology, positions Haib as a potential world-class copper development project, with profound implications for national infrastructure, energy consumption, and regional employment.
The revised plan, which eliminates the previously considered heap leach component from the base case, hinges on a major flowsheet improvement. By adopting a milling and flotation-only approach, Koryx intends to streamline production. A critical element of this optimisation is the application of coarse particle flotation (CPF), an advanced mineral processing method that allows for the efficient recovery of coarse mineral particles up to 450 micrometres. This technology enables the rejection of approximately 12 Mtpa of coarse gangue – waste material – at a grade of just 0.05% copper before the material enters the main flotation circuit.
The economic significance of this technical achievement cannot be overstated. By rejecting waste early, the project avoids the immense capital and operating costs associated with milling barren rock. The remaining 36 Mtpa feed to the main flotation circuit will be of a significantly higher copper grade, directly enhancing the project’s operational efficiency and reducing energy consumption per unit of mineralised material. This is further augmented by the use of Jameson cells in conjunction with conventional flotation, which Koryx states will maintain target copper recovery while facilitating increased final concentrate copper grade and reduced power and space requirements.
Heye Daun, President and CEO of Koryx Copper, expressed confidence in the project’s trajectory. “With conversion drilling now completed for the PFS and our metallurgical, infrastructure and permitting workstreams all advancing in parallel, we remain firmly on track to deliver the Haib PFS before the end of November 2026,” he said. “We are confident that this will be reflected in outstanding production and economic metrics which will benchmark the Haib Copper project as a rapidly advancing, world class copper development project in the south of Namibia.”
The economic multiplier effect of the Haib project is perhaps most evident in its energy and water infrastructure requirements, which are poised to catalyse significant investment in the region. The expected increase in process plant throughput to 48 Mtpa has driven the project’s electricity demand to a maximum of 260 MVA, with annual consumption estimated at a staggering 1.45 TWh. To meet this demand, Koryx has signed a Memorandum of Agreement (MoA) with NamPower. The preferred solution is a 68-kilometre, double-circuit 220kV overhead transmission line from the Harib substation to the mine site, supplemented by solar photovoltaic (PV) generation and Battery Energy Storage Systems (BESS). This strategy is designed to reduce overall energy costs and manage peak tariff periods.
Crucially, the company notes that the project is expected to deliver significant new transmission infrastructure and network upgrades in southern Namibia. These assets, intended to strengthen the regional grid, will ultimately be transferred to NamPower for operation and maintenance. This represents a massive, privately-funded injection into Namibia’s public electricity infrastructure, a legacy benefit that will extend far beyond the life of the mine. NamPower is currently reassessing the implications of the increased load forecast and is expected to provide an updated power supply offer to form the basis of a final agreement.
Water security, a critical concern for any large-scale mining operation in Namibia’s arid south, has also been addressed with a long-term, cost-effective solution. Following a comprehensive option assessment, the Orange River water supply scheme has been selected as the preferred bulk water supply solution. This scheme, comprising a single abstraction point approximately 9 km south of the mine and an off-channel storage reservoir, is deemed both technically feasible and the lowest-cost option. Koryx has signed a Memorandum of Understanding with NamWater, and an Infrastructure Development Agreement is being developed to define implementation, operation, maintenance, and eventual handover arrangements.
The project has also made substantial progress on the regulatory front. Applications for an Environmental Clearance Certificate (ECC) for the Mining License Area and for Water Abstraction from the Orange River were submitted to the Ministry of Environment, Forestry and Tourism (MEFT) on 19 August 2026 and 4 September 2026, respectively. These applications, which include the Environmental and Social Impact Assessment (ESIA) and Environmental Management Plan (EMP), are supported by a comprehensive suite of specialist baseline studies covering biodiversity, water resources, air quality, heritage, and social health.
While many applications are decided within one to three months, Koryx is prudently planning for a review period of up to six months, given the scale and complexity of the project. A potential decision is therefore expected before the end of 2027. The ECC is a critical condition for the granting of the Mining License, for which the company has already applied.
The technical foundation of the PFS is being solidified by an extensive metallurgical test work programme, which is nearing completion. Interim results show excellent continuity from historical work and are supporting the PFS metallurgical assumptions and by-product recovery potential for both copper and molybdenum. The programme for the subsequent Definitive Feasibility Study (DFS) is already underway, with drill core and pilot bulk sample selection having commenced in August. This work is focused on building a comprehensive geo-metallurgical model for the project, planned for 2027.
Furthermore, the project has optimised its tailings storage facility (TSF) site selection. From an initial nine candidate locations, a site has been chosen that can most cost-efficiently contain the full life-of-mine tailings volume of approximately 1.15 billion tonnes in a single facility. This location, the only one able to accept the full quantity, also has a relatively low environmental impact, is proximal to the revised plant location, and offers the added benefit of reduced operating costs through short pumping distances.
The cumulative effect of these developments is a project that is not only technically robust but also economically compelling. The shift to a 48 Mtpa milling operation, the adoption of cost-saving CPF technology, and the strategic partnerships for power and water supply all point to a project designed for long-term, low-cost, and low-risk operation. As the final PFS results are prepared for publication before the end of November 2026, the Haib Copper Project is signalling its potential to become a cornerstone of Namibia’s industrial future, driving infrastructure development, energy generation, and economic growth in the //Kharas region and beyond.